When preparing through-life specification, which of the following requirements should procurement team define besides the physical asset? Select TWO that apply.
A . Customer service
B . Objectives
C . Market analysis
D . Logistics and installation
E . Available substitute
Answer: A, D
Explanation:
Through-life Management involves the life-cycle management of the products, services and activities required to deliver a fully integrated capability to the customer, while reducing the cost of ownership for the customer.
Source: Andrew Graves
With through-life management, buyer not only cares about the physical asset but also other factors like customer services and maintenance.
Reference: CIPS study guide page 130
LO 3, AC 3.2