When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.

When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.
A . False
B. True

Answer: B

Explanation:

When there are n teams in a project, there are:

– 1 Product Backlog

– n Sprint Backlogs each Sprint

– 1 Product Owner

– n Scrum Master roles