When n Scrum teams are working on a product, there are n Sprint Backlogs but only 1 Product Backlog.

When n Scrum teams are working on a product, there are n Sprint Backlogs but only 1 Product Backlog.
A . False
B. True

Answer: B

Explanation:

1 product but n teams working on it = 1 Product Backlog and n Sprint Backlogs.