When must the Product Owner participate in the Daily Scrum? (Choose the best answer)
When must the Product Owner participate in the Daily Scrum? (Choose the best answer)
A . When there are impediments to discuss.
B . When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.
C . When the Scrum Master asks the Product Owner to attend.
D . When the Product Owner needs to represent the stakeholders’ point of view to the Developers.
Answer: B
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments