Consider a scenario that starts with a case A that instantiates a Business Automation Workflow B which, in its turn, invokes an Operational Decision Manager (ODM) rule C.
When looking at the Business Automation Insights events emitted for this sequencing, which two statements are true?
A . In the events of the case A, the trace-id element is set to null.
B . The parent-trace-id of the workflow B is set to the trace-id of case A
C . In the events of the case A, the parent-span-id element is set to null.
D . The trace-id elements of all events in the sequence have the same value.
E . The parent-span-id element of both the workflow B and the ODM rule C have the value of the span-id element of case A
Answer: D,E