You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The portfolio roadmap is used abundantly as an input to 7 processes.
When it comes to managing portfolio value, how is the portfolio roadmap used?
A . Delays in delivery of portfolio component results may adversely affect the value derived from the portfolio
B . It is not used in managing the portfolio value
C . Dependencies shown at the roadmap level have negative impacts on the value realized
D . Dependencies shown at the roadmap level have positive impacts on the value realized
Answer: A