Exam4Training

When is the Sprint Backlog created?

When is the Sprint Backlog created?
A . At the beginning of the project.
B . During the Sprint Planning meeting.
C . Prior to the Sprint Planning meeting.
D . During the Sprint.

Answer: B

Explanation:

The correct answer is B, because the Sprint Backlog is created during the Sprint Planning meeting. The Scrum Guide states that “the Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal.”

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version