When is it allowed for a Scrum Master to cancel a Sprint?
A . When the Sprint Goal is obsolete.
B. When the Developers ask the Scrum Master to do so.
C. The Scrum Master does not have the authority to do this.
Answer: C
Explanation:
It’s done by the Product Owner.