When is a change task for Post Implementation Review created for an unauthorized change?
When is a change task for Post Implementation Review created for an unauthorized change?
A . When the change request moves to Close
B. When a change manager accepts the change
C. When the change request moves to a state of Review
D. When the change request moves to a state of Assess
Answer: C
Latest CIS-ITSM Dumps Valid Version with 434 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments