When is a Business Continuity Plan (BCP) considered to be valid?

When is a Business Continuity Plan (BCP) considered to be valid?
A . When it has been validated by the Business Continuity (BC) manager
B . When it has been validated by the board of directors
C . When it has been validated by all threat scenarios
D . When it has been validated by realistic exercises

Answer: D

Explanation:

Reference: http://www.manchester.gov.uk/info/200039/emergencies/6174/business_continuity_planning/5