When is a Business Continuity Plan (BCP) considered to be valid?
When is a Business Continuity Plan (BCP) considered to be valid?
A . When it has been validated by the Business Continuity (BC) manager
B . When it has been validated by the board of directors
C . When it has been validated by all threat scenarios
D . When it has been validated by realistic exercises
Answer: D
Explanation:
Reference: http://www.manchester.gov.uk/info/200039/emergencies/6174/business_continuity_planning/5
Latest CISSP Dumps Valid Version with 981 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments