Exam4Training

When Huawei air-cooled air conditioner is installed, the required time for maintaining positive pressure in the refrigerant pipeline is () hours.

When Huawei air-cooled air conditioner is installed, the required time for maintaining positive pressure in the refrigerant pipeline is () hours.
A . 8
B . 12
C . 24
D . 36

Answer: C