When estimating initial velocity, the team should most likely:
When estimating initial velocity, the team should most likely:
A . Discuss among the team their expectations of how many story points they can address.
B . Use a Kanban workflow to identify steps and calculate velocity.
C . Use velocity of past iterations or make a calculated guess.
D . Discuss with the customer their expectation for the velocity of producing the product.
Answer: C