When does the Nexus Sprint Planning end?
When does the Nexus Sprint Planning end?
A . When the expected results of the Nexus Sprint Planning are met
B. When all the individual teams finish their Sprint Planning
C. When the Product Owner says so
D. When the representatives of each team meet after the individual teams’ Sprint planning
Answer: A
Explanation:
The Nexus guide no longer prescribes the format of the Nexus Sprint Planning. Instead, it states the purpose and the expected results of the event. This event ends when all the expected results are achieved.