When does the buyer update the status of the Quality Notification to "Complete?

When does the buyer update the status of the Quality Notification to "Complete?
A . When the Quality Notification is updated with a root cause
B . When the Inspection Lot is accepted
C . When the Quality Notification is closed
D . When the Advance Ship Notice is delivered

Answer: A