When do change requests generally increase in a project?
When do change requests generally increase in a project?
A . Towards the beginning of the project.
B . During the project scope management processes.
C . During the project’s launch.
D . Towards the end of the project.
Answer: D
Explanation:
Changes generally increase towards the end of the project. This can be due to a loosely defined scope, lack of requirements, and other reasons.
Answer B is incorrect. The scope management process happens throughout the project until the scope is completed.
Answer C is incorrect. Changes are easier to incorporate at the launch of the project but generally do not happen until later in the project.
Answer A is incorrect. Scope changes generally happen towards the end of the project.
Latest CCBA Dumps Valid Version with 421 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund