When developing the organization’s first risk universe, which of the following would the chief audit executive be least likely to consider?
A . The amount of risk that an organization is willing to seek or accept.
B . The extent and degree of interdependency for identified key risks.
C . The boundaries established to manage the amount of risk taken.
D . The exposure to risks following management’s risk responses.
Answer: D