When creating an operation step in an inspection plan, which of the following is mandatory?

When creating an operation step in an inspection plan, which of the following is mandatory?
A . Work centre
B . Standard text
C . Control key
D . Activity type

Answer: C

Explanation:

Control keys are required when creating the operating steps of an inspection plan in the SAP system. Control keys define the types of operations that can be performed (such as machining, quality inspection, etc.) and specify which functions or operations are allowed. Control keys essentially control the processing logic and possible input types of an operation, and are key settings to ensure that the operation is performed as intended.