When creating an operation step in an inspection plan, which of the following is mandatory?
When creating an operation step in an inspection plan, which of the following is mandatory?
A. Work centre
B. Standard text
C. Control key
D. Activity type
Answer: C
Explanation:
When creating an operation step in an inspection plan in SAP, the A. Work centre is mandatory. It defines where the operation or activity is to be performed. The other options like Standard text, Control key, and Activity type are not mandatory when creating an operation step.