Exam4Training

When can changes to requirements occur in a business analysis planning and monitoring assignment?

When can changes to requirements occur in a business analysis planning and monitoring assignment?
A . Change to requirements can occur any time before the project scope statement is created.
B . Changes to requirements can occur at any time.
C . Changes to requirements can occur any time after the project’s change control system has been enacted.
D . Change to requirements can occur at any time before the key stakeholders approve the identified requirements.

Answer: B

Latest CBAP Dumps Valid Version with 498 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version