Exam4Training

When can a Development Team cancel a Sprint?

When can a Development Team cancel a Sprint?
A . When a technical dependency cannot be resolved.
B . When the selected Product Backlog items for the Sprint become unachievable.
C . When the Product Owner is absent too often.
D . It cannot. Only Product Owners can cancel Sprints.
E . When functional expectations are not well understood.

Answer: D

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version