When calculating the cost of delay, which of the following does not reflect the time criticality?
A . What is the revenue impact on our business?
B. Is there a fixed deadline?
C. What is the current effect on customer satisfaction?
D. Will they wait for us or move to another solution?
Answer: A
Explanation:
https://www.scaledagileframework.com/wsjf/