When an operational area develops a treatment for a critical risk, the risk management professional MUST

When an operational area develops a treatment for a critical risk, the risk management professional MUST
A . add the risk to the risk map.
B. communicate the treatment plan directly with internal audit.
C. evaluate the dollar savings associated with the treatment.
D. evaluate the impact upon other areas.

Answer: D

Explanation:

When an operational area develops a treatment for a critical risk, the risk management professional must evaluate the impact upon other areas3. This helps to ensure that the treatment does not create new risks or adversely affect other objectives.