When an item goes through change control, which of the following must happen as part of a robust configuration management process?

When an item goes through change control, which of the following must happen as part of a robust configuration management process?
A . Costs associated with the change are evaluated and documented.
B . Risks associated with the change are monitored to avoid delays to the project.
C . The item is approved or declined in line with stakeholder expectations.
D . Documents are updated to include any approved changes.

Answer: D