When an Agile project team receives an “emergency request” during an iteration, which is the best first step that the Agile project manager should take?
A . Stop work on unfinished user stories and work on the urgent request.
B . Call a team meeting and change the iteration scope to include the request.
C . Provide the customer with options provided by the project team.
D . Explain that the team cannot do the added work until the next iteration.
Answer: C