When a switch has multiple links connected to a downstream switch, what is the first step that STP takes to prevent loops?
When a switch has multiple links connected to a downstream switch, what is the first step that STP takes to prevent loops?
A . STP elects the root bridge
B . STP selects the root port
C . STP selects the designated port
D . STP blocks one of the ports
Answer: A