What’s the best response for Mark?

Mark is the Product Owner and he asks you, the Scrum Master what burndown charts actually track.

What’s the best response for Mark?
A . Burndown charts will track the remaining work across the project time.
B. Burndown charts will track the value of the work performed by the Development Team.
C. Burndown charts will track work still left in the project.
D. Burndown charts will track the cost of the work.

Answer: A

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments