Exam4Training

What would you answer?

A member of a Scrum Team is interested in understanding the organization’s ability to deliver value. She asks if he can explain what the Time to Market Key Value Area (T2M) can reveal.

What would you answer?
A . The average velocity across all Scrum Teams in the organization.
B. The organization’s ability to quickly deliver new capabilities, services, or products
C. How quickly the organization can develop Products.
D. The average time required to perform a release.

Answer: B

Explanation:

Time-to-Market (T2M): The organization’s ability to quickly deliver new capabilities, services, or products