What would be the critical path(s)?

A project has live finish-to-start (FS) activities

– Activity A takes one day.

– Activity B follows A and takes five days

– Activity C follows B and takes two days.

– Activity D follows B and A and takes two days.

– Activity E is preceded by C and D and takes two days

What would be the critical path(s)?
A . A-B-C-E and A-B-D-E
B . A-B-C-E and A-D-E
C . A-B-D-E
D . A-D-E and A-B-D-E

Answer: D