What would be the critical path(s)?
A project has live finish-to-start (FS) activities
– Activity A takes one day.
– Activity B follows A and takes five days
– Activity C follows B and takes two days.
– Activity D follows B and A and takes two days.
– Activity E is preceded by C and D and takes two days
What would be the critical path(s)?
A . A-B-C-E and A-B-D-E
B . A-B-C-E and A-D-E
C . A-B-D-E
D . A-D-E and A-B-D-E
Answer: D