You are in the process of setting up your organization’s Resources and learn that Resources in France will be working a 35-hour work week.
What will you need to do to set them up with the proper work calendar?
A . As PSA only allows one work calendar, it is best to implement a 40-hour work calendar and then create a validation rule to only allow 35 hours a week.
B . As the Work Calendar mostly impacts Utilization, set them up with a 40-work calendar, and then include the 35-hour hour work week in your utilization calculations.
C . Create a separate 35-hour work calendar and associate it to the French Resources, including any specific French Holidays.
Answer: C