What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer)

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer)
A . Sprint Planning is canceled so refinement can be done first.
B . The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.
C . Nothing in particular.
D . The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin
E . The Developers will find it difficult to create a Sprint forecast they are confident they can meet.

Answer: E