What type of risk response would you choose to mitigate this risk?
You are leading a large-scale information technology project to migrate your company’s data to the latest hardware. The delivery is being led by third-party suppliers, who were not involved in the design phase. The supplier has completed their capacity planning and has raised a potential risk that the current data may exceed the storage capacity of the new hardware purchased.
What type of risk response would you choose to mitigate this risk?
A . Tolerate the risk as there may be sufficient storage capacity.
B . Re-forecast the budget to include the likely additional cost.
C . Use the contingency budget to cover the purchase of additional storage.
D . Transfer the risk to the supplier.
Answer: C
Explanation:
The best approach is to use the contingency budget because:
Defined Risk Response: Contingency budgets are designed to handle identified risks without impacting the project’s main budget.
Stakeholder Agreement: It avoids escalating disputes with suppliers by addressing the issue proactively.
Unsuitable Options:
A: Tolerating the risk is impractical when the risk is confirmed.
B: Re-forecasting creates unnecessary delays and increases costs.
D: Transferring risk to the supplier could damage partnerships.
Latest APM PMQ Dumps Valid Version with 40 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund