What type of information should a project’s configuration status accounting communicate?
What type of information should a project’s configuration status accounting communicate?
A . Budget updates for the project
B . Changes to the project plan
C . Activity on baselined items
D . Change control board minutes
Answer: C
Explanation:
Configuration Status Accounting (CSA) involves recording and reporting the status of configuration items throughout the lifecycle of a project.
This includes:
Status of Configuration Items: Information about the current state of items, including version numbers and change histories.
Baselined Items: Items that have been formally approved and serve as a basis for further development.
Changes and Updates: Documenting any modifications made to the baselined items.
CSA ensures that all stakeholders are informed about the status and history of configuration items.
Reference: "Software Configuration Management Patterns: Effective Teamwork, Practical Integration" by Stephen P. Berczuk and Brad Appleton
IEEE Standard for Software Configuration Management Plans (IEEE Std 828)