You and your project team have identified the project risks and now are analyzing the probability and impact of the risks.
What type of analysis of the risks provides a quick and high-level review of each identified risk event?
A . Quantitative risk analysis
B . Qualitative risk analysis
C . Seven risk responses
D . A risk probability-impact matrix
Answer: B
Explanation:
Qualitative risk analysis is a high-level, fast review of the risk event. Qualitative risk analysis qualifies the risk events for additional analysis.