What type of analysis of the risks provides a quick and high-level review of each identified risk event?

You and your project team have identified the project risks and now are analyzing the probability and impact of the risks.

What type of analysis of the risks provides a quick and high-level review of each identified risk event?
A . Quantitative risk analysis
B . Qualitative risk analysis
C . Seven risk responses
D . A risk probability-impact matrix

Answer: B

Explanation:

Qualitative risk analysis is a high-level, fast review of the risk event. Qualitative risk analysis qualifies the risk events for additional analysis.