What two things should happen with the item?
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team’s Definition of Done.
What two things should happen with the item? (Choose two.)
A . It will be inspected at the Sprint Review and if it is acceptable by the stakeholders then include it in the Increment.
B . Do not include the item in the Increment for the Sprint.
C . Split the item and add the estimation of the completed work to the current Sprint so not to impact the velocity and add the ‘undone’ work to the next Sprint.
D . Estimate the remaining work needed to make it ‘done’ and add it to the Product Backlog for the Product Owner to decide what to do with it.
Answer: BD
Explanation:
At the end of a Sprint, the new Increment must be ‘Done’, which means it must be in useable condition and meet the Scrum Team’s definition of ‘Done’. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and it is used to assess when work is complete on the product Increment.
Latest PSM II Dumps Valid Version with 180 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund