An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product.
What two actions should the project manager take? (Choose two)
A . Ask the stakeholders about the priority of this change
B . Ask the product owner to review the product backlog
C . Ask the team members to analyze the impact of this change
D . Ask the sponsor to approve the change request
E . Ask the team members to include the change in the next iteration
Answer: A,B