What two actions should the project manager take’?
A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take’? (Choose two)
A . Send letters to the neighbors and ask them kindly not to disturb the project.
B . Set up a meeting with neighborhood representatives to win their cooperation
C . Analyze the situation and find out what is causing the neighborhood’s negative attitude.
D . Ask the customer to extend the project deadline to allow time for conflict resolution
E . Ask the mayor of the city to use their authority to stop neighborhood resistance
Answer: B,C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund