What tool or technique should be used to determine whether or not the variances are within acceptable limits?

A project manager must track schedule variances over time.

What tool or technique should be used to determine whether or not the variances are within acceptable limits?
A . Scatter diagram
B . Cause-and-effect diagram
C . Control chart
D . Control panel diagram

Answer: C