What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
A . Queue
B . Teardown time
C . Move time
D . Setup Time

Answer: B D

Explanation:

The time element of midpoint scheduled operations that can be reduced by reduction strategy settings while dispatching are teardown time and setup time. Teardown time is the time required to dismantle the production equipment after the operation is completed. Setup time is the time required to prepare the production equipment before the operation is started. Both teardown time and setup time can be influenced by the reduction strategy settings, which define the percentage of reduction and the minimum duration for each time element. The reduction strategy settings can be maintained in the work center or the routing. The system applies the reduction strategy settings when dispatching the operations to the resources in the planning board or the product view.

Reference: SAP S/4HANA Manufacturing for Planning & Scheduling – Implementation Guide, page 32; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 81.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments