What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
A . Queue
B . Teardown time
C . Move time
D . Setup Time

Answer: A, C