What three things should you advise them first?

An organization is new to Scrum and has hired you to implement Scrum for three Scrum Teams who will be working together on a new Product release.

What three things should you advise them first?
A . The three Scrum Teams should have a shared Definition of Done.
B. There should be three Product Owners, one for each Scrum Team.
C. The three Scrum Teams should have the exact same Definition of Done.
D. Each Scrum Team should have its own Product Backlog.
E. There should be one Product Backlog for all the teams to represent all of the known work needed to be done for the product.
F. There should be only one Product Owner for the three Teams.

Answer: A,E,F

Explanation:

If Scrum Teams become too large, they should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Goal,

Product Backlog, and Product Owner. A Nexus is a group of approximately three to nine Scrum Teams that work together to deliver a single product; it is a connection between people and things. A Nexus has a single Product Owner who manages a single Product Backlog from which the Scrum Teams work. The commitment for the Integrated Increment is the Definition of Done, which defines the state of the integrated work when it meets the quality and measures required for the product. The Increment is done only when integrated, valuable, and usable. The Nexus Integration Team is responsible for a Definition of Done that can be applied to the Integrated Increment developed each Sprint. All Scrum Teams within the Nexus must define and adhere to this Definition of Done. Individual Scrum Teams self-manage to achieve this state. They may choose to apply a more stringent Definition of Done within their own teams, but cannot apply less rigorous criteria than agreed for the Integrated Increment.

In summary, different Scrum Teams working on the same Product (in Nexus) can:

– Have different Sprint Lengths.

– Have different Scrum Masters.

– Have only one Product Owner.

– Have only one Product Backlog.

– Have a shared Definition of Done.

– Make the Definition of Done more rigorous.