What theme estimates the cost of delivering the project?
A . Business Case
B . Change
C . Plans
D . Progress
Answer: C
Explanation:
The Plans theme in PRINCE2® is responsible for estimating the cost of delivering the project. This theme involves the development of plans that outline how, when, and by whom the project’s objectives are to be achieved, including the necessary resources and associated costs.
Reference: PRINCE2® Foundation official documentation and study materials.