What task setting needs to change to allow 4 users to complete this in less than 3 days?

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?
A . Change the Task Duration Type to Effort Driven
B . Change the Task Duration Type to Calculated Work
C . Change the Task Constraint to Fixed Dates
D . Change the Task Constraint to As Soon As Possible

Answer: B

Explanation:

When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.