What takes place during the Closing a Project process?
What takes place during the Closing a Project process?
A . The post-project benefits reviews are performed
B . Ownership of the project’s products is transferred to the customer
C . An End Stage Report is prepared for the final stage
D . The project closure notification is reviewed and approved
Answer: B
Explanation:
During the Closing a Project process in PRINCE2®, the ownership of the project’s products is formally transferred to the customer, ensuring that all deliverables have been accepted and are ready for operational use. This transfer marks the formal completion of the project.
Reference: PRINCE2® Foundation official study guide and materials.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments