What steps in the Portfolio Kanban are most appropriate for running research spikes? (Select 2)

What steps in the Portfolio Kanban are most appropriate for running research spikes? (Select 2)
A . Analysis-spikes help clarify feasibility.
B . Implementing-teams perform spikes as usual
C . Funnel-understand whether the Epic makes sense.
D . Portfolio Backlog-run a spike before pulling into development.

Answer: A, C