What step does Zerto perform first?
You are using Zerto to migrate VMs, and you apply the Move workflow to a VPG.
What step does Zerto perform first?
A . Creating a new checkpoint for the source VM
B . Powering up the target VM
C . Powering down the source VM
D . Promoting data in the journal to the target VM
Answer: A
Explanation:
Zerto first creates a new checkpoint for the source VM during the Move workflow to ensure data consistency and to manage the migration process effectively.