You are the production scheduler at a manufacturing company. The company is not using advanced
warehousing.
You have firmed a planned production order from master planning. The order is ready to be processed.
You now need to process the order in production control.
What should you do first?
A . Report the order as finished
B . Estimate the order
C . Schedule the order
D . Start the order
Answer: B