Exam4Training

What should you do first?

You are the production scheduler at a manufacturing company. The company is not using advanced

warehousing.

You have firmed a planned production order from master planning. The order is ready to be processed.

You now need to process the order in production control.

What should you do first?
A . Report the order as finished
B . Estimate the order
C . Schedule the order
D . Start the order

Answer: B

Latest MB-320 Dumps Valid Version with 141 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version