What should you do?
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
This item has the following Lean setup:
The setup uses a Lean schedule group with a throughput ratio = 2.
The process activity tied to production ow has the following runtime activity times: time = 3 min, per quantity = 1.
The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item’s production ow activity.
What should you do?
A . Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 1.
B . Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
C . Create a route with a runtime = 1, a process quantity = 6, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
D . Create a route with a runtime = 1, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
Answer: B
Latest MB-335 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund