You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar. A machine in the facility is defective and must be closed for repairs for the next two days. You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A . Navigate to the resource group. Change the calendar to closed on the resource group.
B . Navigate to the calendar used for production and close the next two days.
C . Navigate to the resource. Change the calendar to closed on the resource.
D . Navigate to the resource and select Calendar deviations. Set the calendar to closed for the next two days.
Answer: D