What should you do?

You are project manager who uses Project Professional 2013.Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project.The task list contains over 100 items.You need to create a project based on the tasks in the SharePoint list in the most efficient manner.

What should you do?
A . Open the tasks directly from the SharePoint site into Project Professional 2013.
B . Copy and paste the tasks from SharePoint into Project Professional 2013.
C . Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the Import button.
D . Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.

Answer: A